top of page
walkway.jpg

MUNICIPAL WALKING PATH — NASSAU COUNTY

Manhasset, 1,100 Linear Feet of Walking Path, Alongside a Pond, Through a Tree-Lined Corridor That Leaves Zero Room for Error

📍 Manhasset, Nassau County, NY

📅 Completed: August 2022

🏗 1,100 LF · 11,000 sq ft

🌳 Waterfront Adjacent

1,100 LF
Path Length
10 ft
Path Width
11,000
sq ft Total
2.5"
Asphalt Section
Full Length
Concrete Edge Restraints

THE CHALLENGE

Narrow-Width Paving Next to Water, Through a Tree-Lined Corridor, With No Room to Stage Equipment in Any Conventional Way

Most paving jobs have room to maneuver. An open parking lot gives you flexibility — if equipment needs to reposition, there's space to do it. A road has a shoulder. A commercial driveway has adjacent hardscape or open ground.

The Manhasset walking path had none of that.

The path runs 1,100 linear feet alongside a pond in Manhasset, Nassau County. Mature trees line both sides of the corridor. On one side, the pond bank — soft ground that can't take equipment weight without causing bank erosion. On the other side, established landscaping with root systems that have been developing for decades. The path itself is 10 feet wide. The paving machine running the path takes up most of that width.

There is no staging area. There is no room to swing equipment around. Every pass runs the full 1,100-foot length and turns around at the ends. Every haul truck delivering asphalt to the machine has to approach from one end, transfer material, and exit the way it came in.

Narrow-width path paving looks less complex than a large commercial lot. In practice, the constraints are more demanding — not less.

walkway.jpg
3.png
5.png

THE APPROACH

Subgrade First, Edge Restraints Before Paving, One Continuous Pass That Has to Be Right the First Time

Narrow-width path paving requires the kind of preparation that makes the paving operation itself straightforward — because there's no ability to go back and correct mistakes in the middle of a corridor that tight.

The subgrade was prepared and compacted along the full 1,100-foot run before any paving equipment entered the corridor. Grade control on a path this narrow is not about drainage to a basin — it's about ensuring water sheets off the path surface and away from the pond bank, not toward it. The pitch is subtle but critical.

Concrete edge restraints were installed the full length of the path on both sides before paving began. This is the step most narrow-width path work skips — and it's the reason most asphalt paths develop edge crumbling within a few seasons. Without a physical restraint holding the asphalt edge, the mat creeps laterally under foot traffic, the edge loses its density, and water begins entering from the side rather than sheeting off the top. A path built without edge restraints has a finite service life regardless of how well the asphalt itself was installed.

With the subgrade set and edge restraints in place, the paving machine ran the full 1,100 feet in continuous passes — 2.5 inches of hot-mix asphalt surface course over the prepared aggregate base, roller following immediately behind for continuous compaction while the mat was still at temperature. The width meant the roller had very little lateral room for correction — a straight, even pass from start to finish, no ability to pick up and re-run a section without a visible seam.

Five days total. Resident access maintained throughout — no section closed for more than the hours required to lay and cure each pass.

PROJECT SPECIFICATIONS

Full Project Details

LOCATION

Manhasset, Nassau County, NY

Client Type

Municipal / Community Recreation

Total Units

1,100 linear feet

Parking Capacity

10 feet

Total Area

11,000 sq ft

Pavement Section

2.5" hot-mix asphalt surface course · 4" compacted aggregate base

Edge Restraints

Concrete — full path length, both sides

Site Constraints

Waterfront adjacent (pond) · Mature trees both sides · No staging area

Date Completed

August 2022

Crew

Self-performed — Fiorini own crew and equipment

What This Project Demonstrates About Operational Capability

A contractor who can only work in open commercial lots isn't a full-scope paving contractor — they're a parking lot contractor. The Manhasset walking path project required reading a constrained site correctly, planning the approach around real physical limitations, and executing a continuous narrow-width paving operation with no room for error and no ability to stage equipment conventionally. That's what 35-plus years of varied project experience on Long Island builds — the ability to look at a non-standard site and know exactly what it requires.

walkway.jpg

Services Used on This Project

Walkways & Patios

IMG_9805.jpg

Asphalt Paving

IMG_9805.jpg

Paver Installation

IMG_9805.jpg
bottom of page